Edinburgh's North Bridge reopens after eight-year restoration

Edinburgh City Council North BridgeEdinburgh City Council
North Bridge links the Old and New towns of Edinburgh

Edinburgh's North Bridge has finally fully reopened after eight years of restoration efforts.

Work on the Category A-listed bridge, which links the Old and New towns of the capital, first started in 2018 to help safeguard its long-term use.

The bridge has now been completely restored and all four lanes of traffic were operational again on Friday evening. The pavements across the bridge opened earlier in the week.

The original cost of the project was expected to be £22m, but the final cost is expected to be in the region of £86m.

Work to the bridge, which was built in 1897, included grit blasting and repainting all of the structural steelwork, hand finishing the cast iron facade and installing an access platform for future works.

Final completion of the project is expected later this year, but this work will take place below street level and should not create disruption to the public.

Complex project

Edinburgh City Council's transport convener, Stephen Jenkinson, said: "This reopening is all the more welcome given the busy time of year, and the wider travel disruption we're currently experiencing as a result of the fire on Princes Street.

"Make no mistake, this has been one of the most complex and ambitious projects the council has ever undertaken.

"When work first began, some areas of the bridge hadn't seen the light of day in over a century, and few could've imagined the scale of the challenge we faced."

The bridge was constructed almost 130 years ago by Sir William Arroll & Co - the Glasgow firm which also built the Forth Bridge and Tower Bridge in London.

The last major refurbishment was in 1933 and some areas of the structure had not been accessed since the bridge had been completed.

Parts were found in much worse condition than expected, which - along with the Covid pandemic - contributed to the delay.